Tektura wallpaper was also applied to the feature wall areas and corridors.
We were also asked to coat the floors in the refuse areas and used a 2-pack floor paint for longevity.
Finally, Dulux metal shield gloss was applied to metalwork in the stairwells and demarcations were completed in the car park areas to the steelwork and walls.
This project was carried out over a 20-week period through the winter and at its peak had up to 15 operatives on site for the Story Team.
Project Name:
Feethams Premier Inn, Darlington
Client Name:
MCLH
Services:
Painting and Decorating of New Build Hotel
Length of Contract:
7 months
Awards:
Very Highly Commended in the Commercial Category at the Painting and Decorating Association Premier Trophy Awards 2017